Welcome to basement construction part 2. In this section we present step by step process of basement carpentry.
Drywall: Installation, Taping and Two coats of primer.
Stairs (If other than carpet)and Staircase opening installation.
Flooring (If other than carpet).
Door Installation: Door jambs are installed and doors are hung.
Bathroom fixtures are installed and water is connected.
Install tiles in bathroom.
Finish with wood around windows.
Bases, Casings and crown moldings are installed.
Bar is built and installed.
Entertainment center is built and installed.
Painting of trims and doors.
Painting of walls.
Installation of door knobs and door stoppers.
Installation of vent registers.
Carpet Installation (If applicable).
Final inspection.